Antelec Pvt Ltd

Client Overview:

Antelec is an internationally renowned electrical contracting company & is strategically poised to enter MEP Contracting with the capability to offer end to end comprehensive solution to the clients providing Electrical, HVAC, Plumbing and Fire Fighting. Antelec is known for Quality, Safety, Reliability and Timely Delivery of projects undertaken.

Project Situation:

Urgent need for Battery charger for Container Port Terminal with compliance to sea shore salty environment &IEC Standards for HT panel

Complication:

Customer was running against time to start the project at Mumbai container Port terminal in 3-4 weeks. Their earlier vendors were unable to deliver the Battery chargers on time

Question:

Antelec’s challenge was to meet all the requirements in one go and find a suitable vendor who could meet the Quality standards and Delivery challenges

Answer:

What did TechnoVision do for Antelec Pvt Ltd:

  1. Completed the document approval as per the requirement of Port of Singapore Authority via Antelec.
  2. Completed the product manufacturing after receiving approval from the, adhering to manufacturing standards.
  3. Dispatched two numbers of 48 VDC, 60 Ampere Float Cum Boost Battery Chargers in three weeks after Factory Acceptance Test.
  4. Successfully conducted the installation, testing and commissioning alongside HT Breaker panels supplied by ABB Limited.
  5. Executed the project at Jawaharlal Nehru Port, Bharat Mumbai Container Terminal Phase-2 Development.

The customer expressed satisfaction with the fast delivery of materials and the timely completion of all tasks.


Suyash Speciality Engineering

Client Overview:

Suyash Speciality Engineering, established in 2012, is located at Pune, Maharashtra, India. The company specializes in manufacturing and supplying machine parts, lifter parts, and hydraulic cylinders. It has become a prominent supplier in its field.

Project Situation:

The EPC contractor urgently needed to complete the project for the chemical industry. Product compliance with technical requirements was a must. 110 VDC, 75 Ampere FC, and 80 Ampere FCBC Charger (Dual Charger).

Complication:

Approval from the consultants needed to be obtained to ensure that the product was ready within 3 to 4 weeks. Additionally, there was limited time to arrange the materials, adding significant pressure to the process.

Question:

What steps must be taken to arrange the materials as required to begin production while ensuring that technical compliances and manufacturing standards are adhered to?

Answer:

What did TechnoVision do for Suyash Specialty Engineering:

  1. Detailed designing and drawings were submitted for approval
  2. Parallel processing of the product manufacturing to save time
  3. Adhering to manufacturing standards as per approval.
  4. Dispatched one 110 VDC, 75 Ampere FC, and 80 Ampere Dual Float Cum Boost Battery Chargers within four weeks.
  5. Successfully managed the testing, installation, and commissioning alongside turbines supplied by Siemens
  6. Executed the project at DMCC Specialty Chemicals Limited Roha, Raigad, Maharashtra.
  7. The customer expressed satisfaction with the fast delivery of materials and the timely completion of all tasks.

ESBEE Power Solutions Pvt Ltd

Client Overview:

ESBEE Power Solutions Pvt. Ltd. has been a leader in co-generation power plants and top-quality boiler manufacturing for over 16 years. Recognized as a leading manufacturer of power plant equipment, heat exchangers, and pollution control systems, ESBEE consistently designs, manufactures, and delivers co-generation power plants and boilers that surpass industry standards.

Project Situation:

The EPC contractor urgently needed to complete the project for the sugar and cogeneration industry. Product with compliance with Technical requirements was a must. FC-FCBC 110V-40-80A battery chargers #4 with 2V-100Ah to 200Ah VRLA SMF batteries

Complication:

Approval from the consultants needed to be obtained to ensure that the product was ready within 5 to 6 weeks. Additionally, there was limited time to arrange the materials, adding significant pressure to the process.

Question:

What steps must be taken to arrange the materials as required to begin production while ensuring that technical compliances and manufacturing standards are adhered to?

Answer:

What did TechnoVision do for Esbee Power Solutions Pvt. Ltd.:

  1. Detailed designing and drawings were submitted for approval
  2. Parallel processing of the product manufacturing to save time.
  3. Adhering to manufacturing standards as per approval.
  4. Dispatched four 110 VDC, 80/40/35/40 Ampere Dual Float Cum Boost Battery Chargers within five weeks.
  5. Successfully managed the testing, installation, and commissioning alongside turbines supplied by Siemens & Triveni.
  6. Executed the project at Aditya Birla Group Grasim Industries Vilayat, Indian Potash Limited Odisha, Maa Bageshwari Sugar Jalana, and Dabra Alco Brown Madhya Pradesh.
  7. The customer expressed satisfaction with the fast delivery of materials and the timely completion of all tasks.